Archives Project Photos

Project Chronology

Achieved:
May 20 thru June 9- book collection moves
June 10 thru 19 – temporary moves & relocations on 1st floor, preparatory work on 2nd floor
June 20 – construction begins on 2nd floor
June 24 – construction area on 1st floor closed to public
July 15 – steel reinforcement of the 2nd floor slab begins
August – construction concludes on 1st floor
September – construction concludes on 2nd floor
September – high-density shelving installed 2nd floor
September – Periodicals consolidation project begins
October – Move in to new Archives offices & collection areas begins.


archives.project.8-8-2013

8/8 -- the slab reinforcement is finished and the push is on to get first floor ready before the start of the fall semester.

arcdhives.project.7-22-2013.2

7/22 - The structural gridwork.

archives.project.7-22-2013.1

7/22 - Structural steel beams added to the 2nd floor slab. Inset shows the attachment of the beams to the pillars.

Archives.project.7-19-2013

7/19 - Insulation and vapor barriers are installed in the new Archives collections area.

archives.project.7-16-2013.1

7/16 - The structural steel being added to the 2nd floor slab.

archives.project.7-15-2013.2

7/15 - a busy day at the Library . . . cutting steel outside, drilling concrete inside.

archives.project.7-16-2013.1

The bolts that will attach the reinforcing steel beams for the second floor slab.

archives.project.7-15-2013.1

7/15 - Waiting for the steel beams to arrive.

archives-project.7.3.2013

7/3 - Walls come down on 1st floor.

archives-project.6-24-2013.4

6/24 - A close-up shot.

archives-project.6-24-2013.2

6/24 - More materials!

archives-project.6-24-2013.1

Archives-project.6-21-2013.1

6/21 - Demolition procedes in the new University Archives space on the 2nd floor of the Library.

archives-project.6-20-2013.3

6/20 - the crane approaches! Materials for the project will be lifted into the 2nd floor through one of the exterior windows.

archives-project.6.20.2013.2

6/20 - the construction area is draped with plastic to keep down the dust of demolition.

archives-project.6.20.2013.1

6/20 - All the preliminary work is finished. 2nd floor ready for construction to begin.

archives.project.6-13-2012.3

6/11 - the end of the great move. Will they all fit in their new location on the ground floor east side?

archives.project.6-11-2013.2

6/11 - the end of the great book move. The last few books on 2nd floor west will move soon.

archives.project.6-11-2013.1

6/11 - the next stage of construction requires carpet and the underlying floor tiles to be removed.

archives.project.6-10-2013.4

6/10 - the push is on to finish the last of the shelving!

archives.project.6-10-2013.3

6/10 - Our "temporary" compurter lab will consist of 12 computers, 6 mac and 6 windows.

archives.project.6-10-2013.2

6/10. In order to reinforce the floor above the computer lab, all the computers must move.

archives.project.6-10-2013.1

6/10. Almost ready for the next phase. The west side of the 2nd floor is largely emptied of books. The remainder are expected to move today.

archives-6.5.2013

Book carts are lined up waiting for shelves to be constructed as half of the book collection at Cowles Library moves from 2nd floor to the Ground floor.

Archives-5-31-2013.1

Workers from Jones Library Sales begin the move of 200,000+ books to the ground floor. 05.31.2013

archives-5.29.2013-4

Books from the second floor will be relocated on the Ground floor, east side. Current periodicals are transferred and shelving is removed from the area to make room.

archives-5.29.2013.3

Surplus shelving is hauled from the building for recycling.

archives-5.29.2013.2

Removal of books and shelving on the second floor, west side, is underway.

archives-5.29.2013

The floor above the computer lab will be reinforced. Books have already moved out of the area, the computers will follow in a couple of weeks.


Signs of Progress!

West side of 1st floor!

Click for larger image.