Timeline

Preliminary design for Cafe area in the Lower Commons

 

Preliminary design for the main study area in the Lower Commons

Project Timeline

JANUARY 2012

Library planning committee & architect begin work

Core project documents developed

FEBRUARY 2012

Initial building layouts completed

Furniture design begins

MARCH 2012

Preliminary designs presented to Student Senate

APRIL 2012

Preliminary designs presented to Library liaisons

Final finishings selection (chairs, tables, dividers, glassboards, carpeting, fabrics)

Review / Approval by President’s cabinet

MAY 2012

Review / Approval by Board of Trustees

Construction phase begins May 21

JUNE, JULY 2012

(Anticipated) Construction

AUGUST 2012

(Anticipated) Project Completion on or near August 1