Lower Commons Project: Photo Archive

August 2 – today

newest photos display first

LC-9/10

9/10 - New exterior doors on University Avenue are needed for after hours operation.

LC-Project- 08/30 – before&after

8/30 - Before and after.

LC-Project-08/30 – cafelights

8/30 - We're still waiting on some pendant light fixtures above each of the study tables across from the cafe.

LC Project – 08/30 – 4

8/30 - News stories of the week: Hurricane Isaac & the Republican Convention

LC-Project-08/30-3

8/30 - Glassboards and collaboration stations are getting some use.

LC-Project-0830-2

8/30 - Lots of chairs movement means a lot of use. Tables haven't moved as much as expected.

LC-Project-08302012-1

8/30 - Still in it's first week, the Historic Entry reading space is very popular.

LC-Project-8/15-2

8/15 - Drake workers scrubbing floors and moldings in the construction area.

LC-Project-8/15-1

8/15 - Drake workers preparing the construction area for occupancy. Marble stairs get a scrubbing.

LC-Project-8/10

8/10 - Door installation. Opening day is rapidly approaching.

LC-Project 08-08-2012

8/8 - Wall-mount and mobile glassboards serve the same function as whiteboards, but provide better writing surfaces & easier cleanup.

LC-Project – 8/3-2

8/3 - The historic entry -- previously an unused hallway -- will become a transitional study space linking the busy social Lower Commons with the scholarly atmosphere of the Reading Room.

LC-Project-8/3-1

8/3 - Pendant light fixtures installed. On the power wall, darker material is acoustic while lighter material is where the collaboration station 37" monitors will be mounted.)

LC Project- 8/2

8/2 - A "power fence" runs through the middle of the room providing power, noise control and monitor mounts for the collaboration stations.

June 8 – August 1: Construction through arrival of furnishings

newest photos display first

LC-Project-08/01 -1

8/1 -- They CLAIM it's lunch time.

LC-Project-08/01-2

8/1 - New furniture began arriving today! Some assembly required.

LC-Project-7/30-1

7/30 - The new Lower Commons drinking fountain includes a refilling station for water bottles.

LC-project-07/27-2

7/27 - Carpet installation begins.

LC-Project-7/27 – 1

7/27 - Preparing for carpeting is dusty work. A concrete scarifier knocks loose any debris from the floor surface.

LC-Project-7/23

7/23 - Finish work begins on the new doorway.

lc-project-7/19-3

7/19 - Ceiling tiles are installed. Some of the new lighting can be seen along the right side tiles.

lc-project-7-19-2

7/19 - Excavation required for the cafe renovation progresses. The whole is being backfilled in this photo.

lc-project-7-19-1

7/19 - New class and wood frames complete window renovations.

lc-project-7/11-2

7/11 - Laser light is provides the straight line to guide workers when positioning the grid for ceiling tiles.

LC-Project – 7/11 -1

7/11 - A beautiful job of installing new restroom tile makes for an attractive, contemporary look.

7/10 - Ceiling grid installations are well under way.

lc-project-07-10-3

7/10 - Ceiling grids are filling in rapidly.

lc-prject-7/10-2

7/10 - The existing printers in the commons are moved to a new location. There will be an additional printer/copier in the lower commons for after-hours operations!

lc-project-7-10-1

7/10 - New tile installed. The camera is giving a false intensity to the greens -- the green tile is not nearly that bright in color and the floor tile is black.

lc-project-7-9-2

7/9 - New glass replaces the old windows. The new look will match the windows in the Reading Room.

lc-project-7-9-1

7/9 - A very busy start to a very busy day -- lots happening from windows to tile to ceilings.

lc-Project-7/5/2012 -2

7/05 - Floor boxes will bring power into the center of the study space, a key element for modern study using mobile devices like laptops.

lc-Project-07-15-2012-1

7/5 - Windows are updated for energy efficiency and user comfort.

lc-project-6/29-4

6/29 - Dan Sloan, project architect (center), visits the construction area.

Lc-Project-6/29-3

6/29 - The network cables arrive in the Lower Commons.

LC-Project-6/29-2

6/29 - The first new coat of paint is discovered lurking amid the rafters . . .

LC-Project-6/29/-1

6/29 - A general shot of the construction area. There's a lot going on.

Lc-project-6/27

6/27 - Pulling network cables for the Lower Commons.

LC Project – 6/26

6/26 - Takes a lot of work to get to this point. Nearly ready for some painting & ceiling tiles in the next few days.

LC-Project-6/21

6/21 - Converting old, unused display cases into a bay window between the Lower Commons and the building's HIstoric Entry.

LC-Project-6/20

6/20 - The cafe is completely refurbished as part of this project. Here a new cafe wall gets its electrical rough-in.

LC-Project-6/18

6/18 - Room 45 is being renovated into a Library classroom that supports a variety of teaching styles.

LC-Project-6/15

6/15 - The new after-hours door is framed in.

LC-Project-6/14

6/14 - Electrical rough-in and bulkhead work continue throughout the day.

LC-Project-6/13-1

6/13 - Work on enclosing the ceiling bulkheads resumes.

lc-project-7/12

7/12 - preparing some surfaces for painting.

 

May 4 – June 7, 2012:  Preparation, Demolition, Plumbing Rough-In, Bulkhead Rough-In

newest photos display first

LC-Project-6/7-1

6/7 - All cleaned up and ready for inspection.

LC-Project-06/06-2

6/6 - The bulkheads help define areas within the space and add architectural interest.

LC-Project-06/06-1

6/6 - Bulkheads are covered with sheetrock.

LC-Project-6/5/-2

6/5 - The bulkheads are covered with sheetrock.

LC Project- 6/5- 1

6/5 - An early morning shot showing progress on the bulkheads.

LC-project-6/4-1

6/4 - construction continues on the ceiling bulkheads

LC Project – 6/1 – 1

6/1 - a curved bulkhead will define the cafe area.

LC Project – 5/31 -1

5/31 - Ceiling bulkheads provide architectural elements & lighting features in the new space.

LC-Project-5/30-2

5/30 - Framing in new walls and ceiling elements (1 of 2).

LC project – 5/30 – 1

5/30 - Framing in new walls and ceiling elements (2 of 2).

LC-Project – 5/29 – 4

5/29 - considerable progress visible on the plumbing rough-in.

LC Project – 5/29 – 3

5/29 - Not a fireplace. A radiator was removed here for the "after-hours" entry door into the lower commons study space.

LC Project – 5/29 – 2

5/29 - Old display cases will become a bay window looking out into the historic entry.

LC Project – 5/29 – 1

5/29 - Early morning view of construction area. Floor tile is all gone.

LC-Project-5/25-2

5/25 - Removing old flooring (1 of 2).

LC-project-5/25/-1

5/25 - Removing old flooring (2 of 2).

LC project 5/24 -2

5/24 - plumbing rough-in in the basement mechanical room.

lc-project-5/24-1

5/24 - demolition spectacular!

LC-Project-5/23-0600-2

5/23 - The library classroom midway through demolition.

LC-Project – 5/23 – 0600 – 1

5/23 - Quiet and peaceful before work starts on Wednesday morning.

Lower Commons – 5/22 – 3

5/22 - By afternoon, demolition was into the cafe area.

LC-Project-05/22-2

5/22 - Demolition work on the classroom.

LC Project – 05/22 – 1

5/22 - Demolition work on the former classroom.

Lower Commons – 5/21 – 5

5/21 - Looking toward the old classroom.

Lower Commons – 5/21 – 4

5/21 - No more coffee?

Lower Commons – 5/21 – 3

5-21 Cowles Cafe is leaving the building.

project-5/22-2

5/21 - Construction begins! Closing off the work areas.

project-5/21-1

5/21 - Work begins -- demolition.

Construction 6 – 5/17

5/17 - removing older equipment from Room 45 (the temporary classroom for 2012-13).

Construction 5 – 5/17

5/17 - Matt Strum (OIT) picks up equipment to be used in the new classroom.

Construction 4 – 5/14

5/14/2012 - All that furniture has to go somewhere . . .

Construction 3 – 5/14

5/14/2012 - No more classroom. We'll be using room 45 on the lower level for classes in the fall.

Construction 2 – 5/14

5/14/2012 - The cafe area emptied for construction.

Construction 1 – 5/14

5/14/2012 - Removing all furniture from the cafe area to prepare for construction in one week.