Construction Schedule

Week of Work Planned
May 21st set up temp protection, demolish the existing space, begin MEP (mechanical, electrical, plumbing) rough in
May 29th continue demolition and MEP rough in
June 4th through June 22nd Build new restrooms, begin finishes, MEP, new glass at windows
June 25th continue finishes, install decorative glass, MEP trim, refinish millwork
July 2nd ACT and flooring
July 9th Clean, punch, install owner provided items
July 15th Turnover